Depending on Application and weather. (Allow 12 hours on-top of normal curing times when temperatures are below 10 degrees Celsius)
- ST-300 Primer Sealants take approx 12 hours to cure and 24 hours to be operational.
- Titanium Non-Slip will be Semi-operational within 12 hours of application and cured within 30 hours.
- Epoxy colour coats on top of Titanium will be operational within 36 hours and fully cured within 3 days.
- Epoxy Colour Floating Applications will be Semi-operational within 5 days of application and fully cured within 7 days.